Katra-Banihal rail link face hurdles at Tunnel 1 near Katra

‘Main boundary thrust the main cause of delay in completion of the project’

Railways complete Arch closure of world’s highest railway bridge over Chenab in J&K

File Photo

Share on Facebook

Jammu, May 04: As the entire country is waiting to get connected to Kashmir through railway line, the major hurdle which the northern railway is facing is in tunnel 1 near Katra.

The 3.2-km-long tunnel may take another six to seven months to get completed.

According to the news agency—Kashmir News Observer (KNO), taking a train to Kashmir valley has become a herculean task for the northern railways as they had to overcome several technical as well as geological issues in boring tunnels and laying the railway track.

“Though the biggest achievement for Konkan railways, construction agency, was to construct the 359-meter tall world’s highest single arch railway bridge over river Chenab connecting Bakkal and Kauri villages of Reasi district but the construction of Tunnel 1 near Katra is giving tough time to the construction agency,” said a source in Konkan railways.

RelatedPosts

Soldier shoots self dead in J-K Gulmarg

Man killed, 2 injured in Verinag accident

Northern Railways begins commercial operations of Vande Bharat train between Katra and Srinagar

The source said that there was a time when engineers thought of giving up the work on the tunnel but with the use of advanced technology, boring was completed by overcoming all the hurdles. “Now, the heading and benching work is undergoing and with all the difficulties and hurdles like cavities and other things engineers are ensuring the work is completed as soon as possible. Once the heading and benching is completed, laying of track will be done,” he said.

“It may take another six to seven months if things remain alright and no further issues explode,” he added.

The 338-km-long Jammu to Baramulla rail link will connect Kashmir valley with the rest of the country through rail link and besides road and air connectivity, people will be able to reach Kashmir through train.

Geologists had warned the northern railways and executive agency in the beginning of main boundary thrust issue on the line which is having young mountains, presence of water and loose strata. “These mountains have continuous growth which leads to cavity at many places and at times leads to major damage to the structures including the tunnels. The construction agency has to face similar challenges on regular intervals, due to which the project is getting delayed,” the source informed.

Moreover, the train service between Sangaldan and Reasi is almost ready with few smaller technical issues. “Within a month or so it is expected to start the train service between Sangaldan and Reasi which will add another feather to the cap of Konkan railways. Once the green signal is give the train service will pass through the highest railway bridge as well,” he added—(KNO)

ShareTweetSend
Previous Post

7000 pilgrims from Kashmir gear up for annual Hajj pilgrimage

Next Post

Two Militant Associates Arrested Along With Arms And Ammunition in Shopian

Related Posts

Soldier shoots self dead in J-K Gulmarg

June 9, 2025
Udhampur mishap: Four of a family missing, one body recovered

Man killed, 2 injured in Verinag accident

June 8, 2025
Northern Railways begins commercial operations of Vande Bharat train between Katra and Srinagar

Northern Railways begins commercial operations of Vande Bharat train between Katra and Srinagar

June 8, 2025

“Personally Sad for Me, One Day the Govt Will Have to Trust People”: CM Omar Abdullah on Disallowing Prayers at Jama Masjid Srinagar

June 7, 2025

USBRL project features 36 tunnels, 943 bridges; Katra-Banihal section to host India’s longest railway tunnel: Senior Railway Official

June 6, 2025

Pak enemy of peace, development and humanity: PM Modi

June 6, 2025

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Facebook Twitter Instagram Youtube Telegram

About Us

Asia News Observer is a multimedia news portal based in Kashmir region of Jammu & Kashmir. We cover political, social and cultural dissent within the larger context of the conflict and its contours to provide an honest understanding of daily life.

NEWS BY TOPIC

  • Gaming / Technology
  • Health
  • International
  • J&K
  • Lead
  • National
  • News
  • Opinion
  • Special
  • Sports
  • Video

More Info

  • Home
  • Privacy Policy
  • Team
  • Contact Us
  • About Us

© 2020 ASIA NEWS OBSERVER - DESIGNED BY BUUCKET

No Result
View All Result
  • Home
  • J&K
  • Special
  • National
  • Health
  • Sports

© 2020 ASIA NEWS OBSERVER - DESIGNED BY BUUCKET

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
error: Content is protected !!